November 10, 2008
M.T.A. Faces $1.2 Billion Deficit
By Sewell Chan and William Neuman
The Metropolitan Transportation Authority faces a $1.2 billion budget deficit in 2009 — $300 million more than it had projected in July — that will very likely require new fare and toll increases or service reductions unless it gets new state and city aid or finds new sources of revenue, officials warned on Monday morning.
At a meeting of the finance committee of the authority’s board, the authority’s chief executive, Elliot G. Sander, said the authority faces a dire fiscal situation that could influence riders across the subway, bus and commuter-rail networks. The deficit was caused, he said, by the collapse of revenues from real estate and corporate taxes, which until just a few years ago had given the authority a string of healthy surpluses.
“The word draconian is not inappropriate,” Mr. Sander said at a news conference after the meeting. He was flanked by the authority’s chairman, H. Dale Hemmerdinger, and its chief financial officer, Gary J. Dellaverson, in describing the potential service reductions.
“They will be very, very significant,” Mr. Sander said. “Whatever that mix that we come up with, in terms of fare and toll increases and service reductions, there’s no question that they would have an impact, significantly, on our customer and on the functioning of that region.”
The magnitude of the fiscal challenges confronting the authority was evident in a PowerPoint presentation presented at the meeting and posted to the authority’s Web site.
Real estate transaction taxes, which represent an important share of M.T.A. revenue, provided the authority with more than $1.4 billion in 2006 and nearly $1.6 billion in 2007. This year, the authority is on track to collect only $995 million in such taxes — about $50 million less than had been projected in July.
And the situation is expected to get even worse. The authority now expects to collect $895 million in real estate taxes next year, and $877 million in 2010.
The authority is required to pass a balanced budget in December for the fiscal year that starts on Jan. 1. A final decision on the fare and toll increases, and service cuts, will most likely not be reached until after a state commission on M.T.A. finances, appointed by Gov. David A. Paterson and led by a former authority chairman, Richard Ravitch, delivers its report on Dec. 5 and after Mr. Paterson releases the state executive budget on Dec. 16.
The Ravitch commission is contemplating imposing tolls on the four East River bridges — the Brooklyn, Manhattan, Queensboro and Williamsburg Bridges — that are run by the city, unlike the authority’s bridges, like the Triborough, which already charge tolls.
Asked about the toll proposal, Mr. Sander, who was a city transportation commissioner in the Giuliani administration, replied: “I’m previously said that from a broader transportation-policy standpoint, I’m comfortable with that, but that should not be interpreted as my support for it in this context. We are looking at that suggestion, along with many, as we’ve said publicly.”
Mr. Sander attributed the authority’s financial condition to the heavy borrowing for capital projects that occurred in the early part of this decade, when the authority was under the control of Gov. George E. Pataki and the previous chairman, Peter S. Kalikow.
“The 2000-2004 capital program was essentially put on a credit card,” Mr. Sander said, and is “the largest contributor” to the current operating deficit. Already, the heavy borrowing now costs the hundreds of millions of dollars in interest payments each year — and the figure is projected to rise to $2 billion by 2012.
Mr. Paterson said in a statement on Monday:
The financial information provided this morning to the M.T.A. Finance Committee is another reminder of the dire fiscal situation facing all New Yorkers.
In April, I appointed Richard Ravitch to head a commission charged with recommending strategies to fund M.T.A. capital projects and operating needs over the next 10 years, a period when the Authority will be under unprecedented financial pressure as it expands and rebuilds its core infrastructure to provide the additional capacity needed to allow the region to grow. The Commission will report its recommendations in early December.
Addressing the fiscal challenges facing the M.T.A. and the state over the next several years will require shared sacrifice, difficult choices and cooperation from all funding partners. We should be open and transparent in facing these challenges and in discussing options. The M.T.A.’s subway system, buses and extensive regional commuter rail network are the lifelines of the greatest city in the world, and I will continue to work with Richard Ravitch, M.T.A. Chairman Dale Hemmerdinger, M.T.A. C.E.O. and Executive Director Lee Sander, Mayor Bloomberg and the legislative leaders to ensure our transit system continues to serve the 8.5 million people who depend on it each day.
__________________________________
November 10, 2008
October 24, 2008
Important G Train Station Rehab Postponed
Smith-Ninth rehab will cost more and take longer
By Mike McLaughlin
The Brooklyn Paper
It’s the same F-ing story at the crumbling Smith-Ninth Street station: repairs are going to cost more — much more — and take much longer.
As recently as June, the Metropolitan Transportation Authority said it would spend $187.8 million to rebuild the elevated F and G tracks from Carroll Street to Fourth Avenue, and renovate the aging Smith-Ninth street station.
But on Wednesday, MTA spokeswoman Deirdre Parker told The Brooklyn Paper that the work would cost “upwards of a quarter-billion dollars.”
The track work on the so-called Culver Viaduct is still scheduled to begin early next year and finish in 2012.
But the renovation of the decrepit Smith-Ninth street stop — which requires closing the station for ninth months — has been pushed back to 2011 from 2010.
That’s a mixed blessing for straphangers who abhor the conditions at the highest platform in the subway system, but don’t want to have to trek to the Fourth Avenue or Carroll Street portals to hop on a train. (The MTA says it will provide shuttle buses.)
“I think ‘dingy’ is the best way to describe the condition of everything in this station — everywhere you look is just one big, ‘Ew,’” said Jason Coyne, a Carroll Gardens resident. “And now they’re delaying the fix-up process? If it looks like this now, imagine how gross it’s going to be next year, and the year after that.”
That goes double for people who board at the Fourth Avenue station. Last November, the MTA announced it planned to revamp the span over Fourth Avenue by installing expansive windows for views up and down the boulevard. The MTA scrapped that proposal in June due to spiraling budgets throughout the transit agency.
©2008 The Brooklyn Paper
__________________________________
By Mike McLaughlin
The Brooklyn Paper
It’s the same F-ing story at the crumbling Smith-Ninth Street station: repairs are going to cost more — much more — and take much longer.
As recently as June, the Metropolitan Transportation Authority said it would spend $187.8 million to rebuild the elevated F and G tracks from Carroll Street to Fourth Avenue, and renovate the aging Smith-Ninth street station.
But on Wednesday, MTA spokeswoman Deirdre Parker told The Brooklyn Paper that the work would cost “upwards of a quarter-billion dollars.”
The track work on the so-called Culver Viaduct is still scheduled to begin early next year and finish in 2012.
But the renovation of the decrepit Smith-Ninth street stop — which requires closing the station for ninth months — has been pushed back to 2011 from 2010.
That’s a mixed blessing for straphangers who abhor the conditions at the highest platform in the subway system, but don’t want to have to trek to the Fourth Avenue or Carroll Street portals to hop on a train. (The MTA says it will provide shuttle buses.)
“I think ‘dingy’ is the best way to describe the condition of everything in this station — everywhere you look is just one big, ‘Ew,’” said Jason Coyne, a Carroll Gardens resident. “And now they’re delaying the fix-up process? If it looks like this now, imagine how gross it’s going to be next year, and the year after that.”
That goes double for people who board at the Fourth Avenue station. Last November, the MTA announced it planned to revamp the span over Fourth Avenue by installing expansive windows for views up and down the boulevard. The MTA scrapped that proposal in June due to spiraling budgets throughout the transit agency.
©2008 The Brooklyn Paper
__________________________________
September 24, 2008
Brooklyn11211 Blog: G to Have its Own Line Manager?
Neighborhood Threat
All subway lines to get a General Manager
September 22, 2008 at 1:50 pm
Gothamist reports that all subway lines will get a General Manager soon. Currently, the only lines that do have a GM are the 7 and the L. I’m not a daily L rider, but after our experience with the General Manager on the 7 train, I am overjoyed to hear that the G train will soon have a repository for our complaints.
The experiment calls for a general manager to take charge of each subway line and make “quick” decisions over train schedules, maintenance of stations, and riders’ complaints.
We are avid Mets fans and spend 30+ games per year out at Shea. In 2007, the MTA instituted Express service after the games, which (aside from the B61, but we’ve covered that) eliminated any temptation to drive to the game, not when we could be home in half an hour. However, in 2008, they instituted a “Super-Express” which initially only stopped at Woodside, Queensboro Plaza and Grand Central. While we just got off at Queensboro to wait for the B61 (as creepy as it is to do that), the boyfriend wrote to the GM, pointing out that eliminating the Court Square stop deprived riders of the connection to the G.
Three weeks later they wrote back to tell him that three other people also complained of the same thing, and that they had reinstituted that stop. (No, seriously. They even made announcements at Shea about it.) You can read about our adventure here.
If four people could cause that to happen on the 7 train, imagine what a band of determined Greenpoint residents can do to transform G train service.
Coming up: a bus driver reveals the complaint number of the Grand Street depot (after 6 buses went by on Friday OUT OF SERVICE)
__________________________________
All subway lines to get a General Manager
September 22, 2008 at 1:50 pm
Gothamist reports that all subway lines will get a General Manager soon. Currently, the only lines that do have a GM are the 7 and the L. I’m not a daily L rider, but after our experience with the General Manager on the 7 train, I am overjoyed to hear that the G train will soon have a repository for our complaints.
The experiment calls for a general manager to take charge of each subway line and make “quick” decisions over train schedules, maintenance of stations, and riders’ complaints.
We are avid Mets fans and spend 30+ games per year out at Shea. In 2007, the MTA instituted Express service after the games, which (aside from the B61, but we’ve covered that) eliminated any temptation to drive to the game, not when we could be home in half an hour. However, in 2008, they instituted a “Super-Express” which initially only stopped at Woodside, Queensboro Plaza and Grand Central. While we just got off at Queensboro to wait for the B61 (as creepy as it is to do that), the boyfriend wrote to the GM, pointing out that eliminating the Court Square stop deprived riders of the connection to the G.
Three weeks later they wrote back to tell him that three other people also complained of the same thing, and that they had reinstituted that stop. (No, seriously. They even made announcements at Shea about it.) You can read about our adventure here.
If four people could cause that to happen on the 7 train, imagine what a band of determined Greenpoint residents can do to transform G train service.